# Ala. Code § 8-29-4 — Withholding Application and Certification for Payment; Withholding Payment; Notice.

- **Citation**: Ala. Code § 8-29-4
- **Node Type**: section
- **Jurisdiction**: Alabama (state)
- **Code Body**: Code of Alabama 1975 (through the 2026 Regular Session) (Ala. Code)
- **Official Source**: [https://alison.legislature.state.al.us/code-of-alabama#8-29-4](https://alison.legislature.state.al.us/code-of-alabama#8-29-4)
- **Canonical URL**: [https://corpuslaw.us/codes/alabama/title-8/chapter-29/section-8-29-4](https://corpuslaw.us/codes/alabama/title-8/chapter-29/section-8-29-4)
- **Semantic URL**: [https://corpuslaw.us/codes/alabama/title-8/chapter-29/section-8-29-4](https://corpuslaw.us/codes/alabama/title-8/chapter-29/section-8-29-4)

## Hierarchy

Title 8 — Commercial Law and Consumer Protection. > Chapter 29 — Timely Payments to Contractors and Subcontractors.

## Text

8-29-4. Withholding Application and Certification for Payment; Withholding Payment; Notice.

(a) Nothing in this chapter shall prevent the owner, contractor, or subcontractor from withholding application and certification for payment for any of the following reasons if there is a bona fide dispute over one or more of the following:

(1) Unsatisfactory job progress.

(2) Defective construction not remedied.

(3) Disputed work.

(4) Third party claims filed or reasonable evidence that a claim will be filed.

(5) Failure of the contractor, subcontractor, or sub-subcontractor to make timely payments for labor, equipment, and materials.

(6) Property damage to owner, contractor, or subcontractor.

(7) Reasonable evidence that the contract, subcontract, or sub-subcontract cannot be completed for the unpaid balance of the contract or contract sum.

(b) In the event that there is a bona fide dispute over all or any portion of the amount due on a progress payment from the owner, contractor, or subcontractor then the owner, contractor, or subcontractor may withhold payment in an amount not to exceed 2 times the disputed amount.

(c) An owner is required to notify a contractor in writing within 15 days of receipt of any disputed request for payment. A contractor, subcontractor and sub-subcontractor is required to provide written notification within 5 days of disputed request for payment or notice of disputed request for payment.

(Acts 1995, No. 95-380, p. 775, §4.)