> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Cal. Public Contract Code - PCC § 4108. — Section 4108.

- **Citation**: Cal. Public Contract Code - PCC § 4108.
- **Node Type**: section
- **Jurisdiction**: California (state)
- **Code Body**: Public Contract Code - PCC (PCC)
- **Official Source**: [https://downloads.leginfo.legislature.ca.gov/pubinfo_2025.zip](https://downloads.leginfo.legislature.ca.gov/pubinfo_2025.zip)
- **Canonical URL**: [https://corpuslaw.us/codes/california/public-contract-code/division-2/part-1/chapter-4/section-4108](https://corpuslaw.us/codes/california/public-contract-code/division-2/part-1/chapter-4/section-4108)
- **Semantic URL**: [https://corpuslaw.us/codes/california/public-contract-code/division-2/part-1/chapter-4/section-4108](https://corpuslaw.us/codes/california/public-contract-code/division-2/part-1/chapter-4/section-4108)

## Hierarchy

Title PCC — Public Contract Code - PCC > Division 2. — ARTICLE 3. Compost and Co-compost Products [12180. - 12184.] > Part 1. — PART 1. ADMINISTRATIVE PROVISIONS [1100. - 9204.] > Chapter 4. — CHAPTER 4. Subletting and Subcontracting [4100. - 4114.]

## Text

(a)

It shall be the responsibility of each subcontractor submitting bids to a prime contractor to be prepared to submit a faithful performance and payment bond or bonds if so requested by the prime contractor.

(b)

In the event any subcontractor submitting a bid to a prime contractor does not, upon the request of the prime contractor and at the expense of the prime contractor at the established charge or premium therefor, furnish to the prime contractor a bond or bonds issued by an admitted surety wherein the prime contractor shall be named the obligee, guaranteeing
				  prompt and faithful performance of the subcontract and the payment of all claims for labor and materials furnished or used in and about the work to be done and performed under the subcontract, the prime contractor may reject the bid and make a substitution of another subcontractor subject to Section 4107.

(c)

(1)

The bond or bonds may be required under this section only if the prime contractor in his or her written or published request for subbids clearly specifies the amount and requirements of the bond or bonds.

(2)

If the expense of the bond or bonds required under this section is to be borne by the subcontractor, that requirement shall also be specified in the prime contractor’s written or published request for subbids.

(3)

The prime contractor’s failure to specify bond requirements, in
				  accordance with this subdivision, in the written or published request for subbids shall preclude the prime contractor from imposing bond requirements under this section.
