> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Conn. Gen. Stat. § 16a-38f — Agency decision outlines.

- **Citation**: Conn. Gen. Stat. § 16a-38f
- **Node Type**: section
- **Jurisdiction**: Connecticut (state)
- **Code Body**: General Statutes of Connecticut (revised to January 1, 2025, with 2026 Supplement) (Conn. Gen. Stat.)
- **Official Source**: [https://www.cga.ct.gov/current/pub/chap_298.htm#sec_16a-38f](https://www.cga.ct.gov/current/pub/chap_298.htm#sec_16a-38f)
- **Canonical URL**: [https://corpuslaw.us/codes/connecticut/title-16a/chapter-298/section-16a-38f](https://corpuslaw.us/codes/connecticut/title-16a/chapter-298/section-16a-38f)
- **Semantic URL**: [https://corpuslaw.us/codes/connecticut/title-16a/chapter-298/section-16a-38f](https://corpuslaw.us/codes/connecticut/title-16a/chapter-298/section-16a-38f)

## Hierarchy

Title 16a — Planning and Energy Policy > Chapter 298 — Energy Utilization and Conservation

## Text

16a-38f. Agency decision outlines.

Any agency having authority to make any agency decision with respect to an energy-saving capital project which has been designated as a priority energy project shall provide the commissioner with a decision outline within thirty days after such designation. Such decision outline shall include a statement of necessary actions to be taken by such agency, a schedule for completing such actions and a list of actions required of the agency of the state which requested the designation.