# O.C.G.A. § 36-91-24 — Liquidated damages and other incentive provisions for project completion.

- **Citation**: O.C.G.A. § 36-91-24
- **Node Type**: section
- **Jurisdiction**: Georgia (state)
- **Code Body**: Official Code of Georgia Annotated (volumes rebuilt with Ga. L. through the 2026 session; partial) (O.C.G.A.)
- **Official Source**: [https://archive.org/download/gov.ga.ocga.2024/T35-36%20%28V27%29%202019.txt](https://archive.org/download/gov.ga.ocga.2024/T35-36%20%28V27%29%202019.txt)
- **Canonical URL**: [https://corpuslaw.us/codes/georgia/title-36/chapter-91/article-2/section-36-91-24](https://corpuslaw.us/codes/georgia/title-36/chapter-91/article-2/section-36-91-24)
- **Semantic URL**: [https://corpuslaw.us/codes/georgia/title-36/chapter-91/article-2/section-36-91-24](https://corpuslaw.us/codes/georgia/title-36/chapter-91/article-2/section-36-91-24)

## Hierarchy

Title 36 — Local Government > Chapter 91 — Public Works Bidding > Article 2 — Contracting and Bidding Requirements

## Text

36-91-24. Liquidated damages and other incentive provisions for project completion.

Public works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value. The terms of the liquidated damages provisions and the incentive provisions shall be established in advance as a part of the construction contract and included within the terms of the bid or proposal.

Code 1981, § 36-91-24, enacted by Ga. L. 2013, p. 628, § 6/SB 179.