> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# 815 ILCS 603/15

- **Citation**: 815 ILCS 603/15
- **Node Type**: section
- **Jurisdiction**: Illinois (state)
- **Code Body**: Illinois Compiled Statutes (Aug. 2026 snapshot) (ILCS)
- **Official Source**: [https://www.ilga.gov/legislation/ilcs/ilcs.asp](https://www.ilga.gov/legislation/ilcs/ilcs.asp)
- **Canonical URL**: [https://corpuslaw.us/codes/illinois/chapter-815/part-603/section-15](https://corpuslaw.us/codes/illinois/chapter-815/part-603/section-15)
- **Semantic URL**: [https://corpuslaw.us/codes/illinois/chapter-815/part-603/section-15](https://corpuslaw.us/codes/illinois/chapter-815/part-603/section-15)

## Hierarchy

Chapter 815 > Part 603

## Text

(815 ILCS 603/15) Sec. 15. Interest; suspension of performance. (a) If a payment due pursuant to the provisions of this Act is not made in a timely manner, the delinquent party shall be liable for the amount of that payment, plus interest at a rate equal to 10% per annum. (b) A contractor or subcontractor who is not paid as required by this Act may, after providing 7 calendar days' written notice to the party failing to make the required payment, suspend performance of a construction contract without penalty for breach of contract, until the payment required pursuant to this Act is made. (c) The interest imposed by this Act shall not be duplicative of the interest charged under the Mechanics Lien Act. (Source: P.A. 95-567, eff. 8-31-07.)