# Ind. Code ch. 8-1-7.9

- **Citation**: Ind. Code ch. 8-1-7.9
- **Node Type**: chapter
- **Jurisdiction**: Indiana (state)
- **Code Body**: Indiana Code (Aug. 2026 snapshot) (Ind. Code)
- **Official Source**: [https://iga.in.gov/laws/2026/ic/titles/8](https://iga.in.gov/laws/2026/ic/titles/8)
- **Canonical URL**: [https://corpuslaw.us/codes/indiana/title-8/chapter-8-1-7-9](https://corpuslaw.us/codes/indiana/title-8/chapter-8-1-7-9)
- **Semantic URL**: [https://corpuslaw.us/codes/indiana/title-8/chapter-8-1-7-9](https://corpuslaw.us/codes/indiana/title-8/chapter-8-1-7-9)

## Hierarchy

Title 8

## Sections

| Citation | Heading | Type | Link |
| --- | --- | --- | --- |
| Ind. Code § 8-1-7.9-1 | "Acquisition" | section | [View](https://corpuslaw.us/code/bf674176-2f55-412f-8aee-bd3c6b11899f.md) |
| Ind. Code § 8-1-7.9-2 | "Acquisition costs" | section | [View](https://corpuslaw.us/code/527d0248-f617-412b-8848-222b7499308f.md) |
| Ind. Code § 8-1-7.9-3 | "Appropriate regional transmission organization" | section | [View](https://corpuslaw.us/code/4237d7f6-8b4a-4c14-99db-9782a3578df3.md) |
| Ind. Code § 8-1-7.9-4 | "Commission" | section | [View](https://corpuslaw.us/code/e3a6f590-157c-44f3-a870-25cb75a2246d.md) |
| Ind. Code § 8-1-7.9-5 | "Construction and operating costs" | section | [View](https://corpuslaw.us/code/c87f43eb-7370-4740-a611-91f751638622.md) |
| Ind. Code § 8-1-7.9-6 | "Corporation" | section | [View](https://corpuslaw.us/code/4a2fe808-80c0-4086-bafd-2d4a4c43a3ac.md) |
| Ind. Code § 8-1-7.9-7 | "Energy utility" | section | [View](https://corpuslaw.us/code/cc49582c-e96e-4435-a267-a661dcbe8019.md) |
| Ind. Code § 8-1-7.9-8 | "Expedited generation resource plan" | section | [View](https://corpuslaw.us/code/bbf03726-799d-4b90-8cdf-6ea9e0756466.md) |
| Ind. Code § 8-1-7.9-9 | "Generation resource submittal" | section | [View](https://corpuslaw.us/code/37db1769-25dd-4dd6-bf16-9d43c71e6b59.md) |
| Ind. Code § 8-1-7.9-10 | "Large load customer" | section | [View](https://corpuslaw.us/code/07d2e010-2797-4c2a-a07a-99ffe1160342.md) |
| Ind. Code § 8-1-7.9-11 | "Office" | section | [View](https://corpuslaw.us/code/da529782-2163-4503-857b-6e48a6fbdf9b.md) |
| Ind. Code § 8-1-7.9-12 | "Planning costs" | section | [View](https://corpuslaw.us/code/705d4d69-07cc-41ec-8fe2-6ac7ce1af5cc.md) |
| Ind. Code § 8-1-7.9-13 | "Pre-filing meeting" | section | [View](https://corpuslaw.us/code/8c663ada-6c33-42b1-b6f8-f7f8473f9c8d.md) |
| Ind. Code § 8-1-7.9-14 | "Project" | section | [View](https://corpuslaw.us/code/73b95e26-5cb1-482a-b8d0-b80a2ae42165.md) |
| Ind. Code § 8-1-7.9-15 | "Project costs" | section | [View](https://corpuslaw.us/code/0a8c8d5d-b420-4281-86cd-6774e5baae04.md) |
| Ind. Code § 8-1-7.9-16 | "Reasonable risk premium" | section | [View](https://corpuslaw.us/code/44d1e29a-7a83-4d42-8213-ecf2d7997c84.md) |
| Ind. Code § 8-1-7.9-17 | Expedited review of EGR plans and large load customer projects; approval under other statutes not precluded | section | [View](https://corpuslaw.us/code/b0ceb5a1-18f3-4f43-b226-49409927422d.md) |
| Ind. Code § 8-1-7.9-18 | Petition for approval of EGR plan; required information | section | [View](https://corpuslaw.us/code/f57e5a6b-3e6c-497f-bcbc-96c30d28d7c9.md) |
| Ind. Code § 8-1-7.9-19 | Petition for approval of EGR plan; commission's final order; time frame for issuance | section | [View](https://corpuslaw.us/code/84cafa38-ea2e-4395-8837-c074061c7515.md) |
| Ind. Code § 8-1-7.9-20 | Generation resource submittal; required information; acquisition in accordance with approved EGR plan | section | [View](https://corpuslaw.us/code/2ef72289-8458-406c-bc20-ea1f046fcd2f.md) |
| Ind. Code § 8-1-7.9-21 | Generation resource submittal; commission's final order; time frame for issuance | section | [View](https://corpuslaw.us/code/ee449ea7-c46a-431a-9a12-8663dafdae99.md) |
| Ind. Code § 8-1-7.9-22 | Petition for approval of project to serve large load customer; requirements for submission; financial assurances by large load customer; projects serving multiple locations or customers | section | [View](https://corpuslaw.us/code/074265ef-b0ae-40c7-94e2-54baa0d3869c.md) |
| Ind. Code § 8-1-7.9-23 | Petition for approval of project to serve large load customer; required information; case in chief; notice of filing | section | [View](https://corpuslaw.us/code/f1af41f5-3cc9-4bcc-bf00-4a4b70f3e724.md) |
| Ind. Code § 8-1-7.9-24 | Petition for approval of project to serve large load customer; commission's final order; time frame for issuance; reasonable risk premium; approval of acquisition of generation resource; required findings by commission; large load customer no longer requiring service; notice to commission; investigation; modification or revocation of order | section | [View](https://corpuslaw.us/code/7f032103-ad22-4065-aacf-f2458e8c3520.md) |
| Ind. Code § 8-1-7.9-25 | Commission's review of energy utility's estimated acquisition costs or project costs; recovery of costs | section | [View](https://corpuslaw.us/code/86d2fb5a-fcd0-449d-8d49-b492180242fd.md) |
| Ind. Code § 8-1-7.9-26 | Information filed or submitted; treatment as confidential; nondisclosure agreements; corporation's negotiations for economic development project; determination of increased energy demand; notice to affected energy utility; requests and incentives under other statutes; progress reports | section | [View](https://corpuslaw.us/code/c4f076cf-7ae6-4e2b-a00c-924300e6719b.md) |