> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Minn. Stat. § 161.3414 — DETERMINATION TO USE DESIGN-BUILD SELECTION METHOD.

- **Citation**: Minn. Stat. § 161.3414
- **Node Type**: section
- **Jurisdiction**: Minnesota (state)
- **Code Body**: Minnesota Statutes (2025 edition) (Minn. Stat.)
- **Official Source**: [https://www.revisor.mn.gov/statutes/cite/161.3414](https://www.revisor.mn.gov/statutes/cite/161.3414)
- **Canonical URL**: [https://corpuslaw.us/codes/minnesota/chapter-161/section-161-3414](https://corpuslaw.us/codes/minnesota/chapter-161/section-161-3414)
- **Semantic URL**: [https://corpuslaw.us/codes/minnesota/chapter-161/section-161-3414](https://corpuslaw.us/codes/minnesota/chapter-161/section-161-3414)

## Hierarchy

Chapter 161 — TRUNK HIGHWAYS

## Text

161.3414. DETERMINATION TO USE DESIGN-BUILD SELECTION METHOD.

Subdivision 1. General criteria.
A design-build contracting procedure authorized under sections 161.3410 to 161.3426 may be used for a specific project only after the commissioner determines that awarding a design-build contract will serve the public interest.

Subd. 2. Specific criteria.
The commissioner shall use the following criteria as the minimum basis for determining when to use the design-build method of project delivery:

(1) the extent to which it can adequately define the project requirements in a proposed scope of the design and construction desired;

(2) the time constraints for delivery of the project;

(3) the capability and experience of potential contractors with the design-build method of project delivery or similar experience;

(4) the suitability of the project for use of the design-build method of project delivery with respect to time, schedule, costs, and quality factors;

(5) the capability of the Department of Transportation to manage the project, including the employment of experienced personnel or outside consultants;

(6) the capability of the Department of Transportation to oversee the project with individuals or design-build firms who are familiar and experienced with the design-build method of project delivery or similar experience;

(7) the lack of ability and availability of any current state employee to perform the services called for by the contract;

(8) the original character of the product or the services;

(9) the work to be performed on the project is necessary to the agency's achievement of its statutory responsibilities and there is statutory authority to enter into the contract; and

(10) other criteria the commissioner deems relevant and states in writing in its determination to utilize the design-build method of project delivery.

1Sp2001 c 8 art 3 s 3; 2014 c 227 art 2 s 5