# Neb. Rev. Stat. § 39-2811 — Guidelines; contents.

- **Citation**: Neb. Rev. Stat. § 39-2811
- **Node Type**: section
- **Jurisdiction**: Nebraska (state)
- **Code Body**: Nebraska Revised Statutes (through Laws 2026) (Neb. Rev. Stat.)
- **Official Source**: [https://nebraskalegislature.gov/laws/statutes.php?statute=39-2811](https://nebraskalegislature.gov/laws/statutes.php?statute=39-2811)
- **Canonical URL**: [https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2811](https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2811)
- **Semantic URL**: [https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2811](https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2811)

## Hierarchy

Chapter 39 — HIGHWAYS AND BRIDGES

## Text

39-2811. Guidelines; contents.

The department shall adopt guidelines for entering into a design-build contract, a progressive design-build contract, or construction manager-general contractor contract. If a political subdivision intends to proceed with a design-build contract, a progressive design-build contract, or a construction manager-general contractor contract, the political subdivision may adopt the guidelines published by the department. The department's guidelines shall include the following:

(1) Preparation and content of requests for qualifications;

(2) Preparation and content of requests for proposals;

(3) Qualification and short-listing of design-builders, progressive design-builders, and construction managers. The guidelines shall provide that the contracting agency will evaluate prospective design-builders, progressive design-builders, and construction managers based on the information submitted to the contracting agency in response to a request for qualifications and will select a short list of design-builders, progressive design-builders, or construction managers who shall be considered qualified and eligible to respond to the request for proposals;

(4) Preparation and submittal of proposals;

(5) Procedures and standards for evaluating proposals;

(6) Procedures for negotiations between the contracting agency and the design-builders, progressive design-builders, or construction managers submitting proposals prior to the acceptance of a proposal if any such negotiations are contemplated;

(7) Procedures for the evaluation of construction under a design-build contract or a progressive design-build contract to determine adherence to the project performance criteria; and

(8) Procedures for the receipt and evaluation of an unsolicited proposal pursuant to section 39-2811.01.

Laws 2016, LB960, § 11; Laws 2019, LB583, § 6; Laws 2022, LB1016, § 5; Laws 2026, LB1126, § 69. Effective Date: July 18, 2026