# Neb. Rev. Stat. § 39-2812 — Process; provisions applicable.

- **Citation**: Neb. Rev. Stat. § 39-2812
- **Node Type**: section
- **Jurisdiction**: Nebraska (state)
- **Code Body**: Nebraska Revised Statutes (through Laws 2026) (Neb. Rev. Stat.)
- **Official Source**: [https://nebraskalegislature.gov/laws/statutes.php?statute=39-2812](https://nebraskalegislature.gov/laws/statutes.php?statute=39-2812)
- **Canonical URL**: [https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2812](https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2812)
- **Semantic URL**: [https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2812](https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2812)

## Hierarchy

Chapter 39 — HIGHWAYS AND BRIDGES

## Text

39-2812. Process; provisions applicable.

(1) The process for selecting a design-builder and entering into a design-build contract shall be in accordance with sections 39-2813 to 39-2816.

(2) Except as otherwise specifically provided in the Transportation Innovation Act, the process for selecting a progressive design-builder and entering into a progressive design-build contract shall be in accordance with sections 39-2813 to 39-2816.

Laws 2016, LB960, § 12; Laws 2022, LB1016, § 6.