> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Neb. Rev. Stat. § 39-2821 — Contracts; changes authorized.

- **Citation**: Neb. Rev. Stat. § 39-2821
- **Node Type**: section
- **Jurisdiction**: Nebraska (state)
- **Code Body**: Nebraska Revised Statutes (through Laws 2026) (Neb. Rev. Stat.)
- **Official Source**: [https://nebraskalegislature.gov/laws/statutes.php?statute=39-2821](https://nebraskalegislature.gov/laws/statutes.php?statute=39-2821)
- **Canonical URL**: [https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2821](https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2821)
- **Semantic URL**: [https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2821](https://corpuslaw.us/codes/nebraska/chapter-39/section-39-2821)

## Hierarchy

Chapter 39 — HIGHWAYS AND BRIDGES

## Text

39-2821. Contracts; changes authorized.

A design-build contract, a progressive design-build contract, and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit the contracting agency in agreement with the design-builder, progressive design-builder, or construction manager to make changes in the project without invalidating the contract.

Laws 2016, LB960, § 21; Laws 2019, LB583, § 15; Laws 2022, LB1016, § 10.