# Neb. Rev. Stat. § 70-1906 — Construction of new renewable generation facilities; electric supplier; governing body; duties.

- **Citation**: Neb. Rev. Stat. § 70-1906
- **Node Type**: section
- **Jurisdiction**: Nebraska (state)
- **Code Body**: Nebraska Revised Statutes (through Laws 2026) (Neb. Rev. Stat.)
- **Official Source**: [https://nebraskalegislature.gov/laws/statutes.php?statute=70-1906](https://nebraskalegislature.gov/laws/statutes.php?statute=70-1906)
- **Canonical URL**: [https://corpuslaw.us/codes/nebraska/chapter-70/section-70-1906](https://corpuslaw.us/codes/nebraska/chapter-70/section-70-1906)
- **Semantic URL**: [https://corpuslaw.us/codes/nebraska/chapter-70/section-70-1906](https://corpuslaw.us/codes/nebraska/chapter-70/section-70-1906)

## Hierarchy

Chapter 70 — POWER DISTRICTS AND CORPORATIONS

## Text

70-1906. Construction of new renewable generation facilities; electric supplier; governing body; duties.

The governing body of an electric supplier that has determined a need to construct new renewable generation facilities shall take reasonable steps to determine if one or more C-BED projects are available and are technically, economically, and operationally feasible to provide some or all of the identified generation need.

Laws 2007, LB629, § 6; Laws 2016, LB736, § 4.