> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Neb. Rev. Stat. § 70-2204 — Public power suppliers; procedures for load management.

- **Citation**: Neb. Rev. Stat. § 70-2204
- **Node Type**: section
- **Jurisdiction**: Nebraska (state)
- **Code Body**: Nebraska Revised Statutes (through Laws 2026) (Neb. Rev. Stat.)
- **Official Source**: [https://nebraskalegislature.gov/laws/statutes.php?statute=70-2204](https://nebraskalegislature.gov/laws/statutes.php?statute=70-2204)
- **Canonical URL**: [https://corpuslaw.us/codes/nebraska/chapter-70/section-70-2204](https://corpuslaw.us/codes/nebraska/chapter-70/section-70-2204)
- **Semantic URL**: [https://corpuslaw.us/codes/nebraska/chapter-70/section-70-2204](https://corpuslaw.us/codes/nebraska/chapter-70/section-70-2204)

## Hierarchy

Chapter 70 — POWER DISTRICTS AND CORPORATIONS

## Text

70-2204. Public power suppliers; procedures for load management.

Public power suppliers shall develop a procedure to:

(1) Procure demand response, reductions, and load flexibility from large load customers; and

(2) In the event of grid instability or an emergency condition, require the affected large load customers to curtail load or, for those customers with onsite backup generating facilities, to deploy such facilities for the duration of the grid instability or emergency condition or until the load can be recalled safely.

Laws 2026, LB1010, § 4. Effective Date: July 18, 2026