> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Neb. Rev. Stat. § 73-1104 — Design-build contract or construction manager-general contractor contract; authorized; approval required; procedure.

- **Citation**: Neb. Rev. Stat. § 73-1104
- **Node Type**: section
- **Jurisdiction**: Nebraska (state)
- **Code Body**: Nebraska Revised Statutes (through Laws 2026) (Neb. Rev. Stat.)
- **Official Source**: [https://nebraskalegislature.gov/laws/statutes.php?statute=73-1104](https://nebraskalegislature.gov/laws/statutes.php?statute=73-1104)
- **Canonical URL**: [https://corpuslaw.us/codes/nebraska/chapter-73/section-73-1104](https://corpuslaw.us/codes/nebraska/chapter-73/section-73-1104)
- **Semantic URL**: [https://corpuslaw.us/codes/nebraska/chapter-73/section-73-1104](https://corpuslaw.us/codes/nebraska/chapter-73/section-73-1104)

## Hierarchy

Chapter 73 — PUBLIC LETTINGS AND CONTRACTS

## Text

73-1104. Design-build contract or construction manager-general contractor contract; authorized; approval required; procedure.

(1) An authorized agency, in accordance with the State Building Construction Alternatives Act, may solicit and execute a design-build contract or a construction manager-general contractor contract for state buildings for which the authorized agency has responsibility except as otherwise provided in section 73-1103.

(2) Before executing a design-build contract or construction manager-general contractor contract, an authorized agency shall submit a request for approval from the Director of Administrative Services or his or her designee. The request shall include the following:

(a) A written determination that, due to the nature, detail, or circumstances of a project, the use of a design-build contract or construction manager-general contractor contract is justified. The determination shall include a description of facts justifying such use and state whether the authorized agency is planning to use a design-build contract or a construction manager-general contractor contract;

(b) The criteria for making such determination, including the following factors:

(i) The cost of the project;

(ii) The anticipated schedule for the project from preparation for contracting through completion of construction;

(iii) The overall complexity of the project;

(iv) The need to overlap design and construction phases of the project; or

(v) An emergency exists that requires the use of an accelerated schedule to make repairs; and

(c) An explanation of how using a design-build contract or construction manager-general contractor contract will not result in favoritism or substantially diminish competition in awarding such contract for such project.

Laws 2025, LB660, § 4.