# Nev. Rev. Stat. § 11.2055 — Actions for damages for injury or wrongful death caused by deficiency in construction of improvements to real property: Determination of date of substantial completion of improvement to real property.

- **Citation**: Nev. Rev. Stat. § 11.2055
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-011.html](https://www.leg.state.nv.us/nrs/NRS-011.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-2055](https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-2055)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-2055](https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-2055)

## Hierarchy

Title 2 — CIVIL PRACTICE > Chapter 11 — LIMITATION OF ACTIONS

## Text

1. Except as otherwise provided in subsection 2, for the purposes of this section and NRS 11.202 , the date of substantial completion of an improvement to real property shall be deemed to be the date on which:

(a) The final building inspection of the improvement is conducted;

(b) A notice of completion is issued for the improvement; or

(c) A certificate of occupancy is issued for the improvement,

Ê whichever occurs later.

2. If none of the events described in subsection 1 occurs, the date of substantial completion of an improvement to real property must be determined by the rules of the common law.