# Nev. Rev. Stat. § 11.208 — Action by contractor against Department of Transportation upon contract for construction, reconstruction, improvement or maintenance of highway.

- **Citation**: Nev. Rev. Stat. § 11.208
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-011.html](https://www.leg.state.nv.us/nrs/NRS-011.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-208](https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-208)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-208](https://corpuslaw.us/codes/nevada/title-2/chapter-11/section-11-208)

## Hierarchy

Title 2 — CIVIL PRACTICE > Chapter 11 — LIMITATION OF ACTIONS

## Text

An action by a contractor against the Department of Transportation upon a contract for the construction, reconstruction, improvement or maintenance of a highway must be commenced within 3 years after the date of the:

1. Completion of the contract; or

2. Determination of the engineer or decision of the Board of Directors of the Department of Transportation on an appeal of a claim arising from the contract as provided in the standard specifications for construction of roads and bridges adopted by the Department,

Ê whichever occurs later.