# Nev. Rev. Stat. § 338.610 — Subcontractor to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers.

- **Citation**: Nev. Rev. Stat. § 338.610
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-338.html](https://www.leg.state.nv.us/nrs/NRS-338.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-28/chapter-338/section-338-610](https://corpuslaw.us/codes/nevada/title-28/chapter-338/section-338-610)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-28/chapter-338/section-338-610](https://corpuslaw.us/codes/nevada/title-28/chapter-338/section-338-610)

## Hierarchy

Title 28 — PUBLIC WORKS AND PLANNING > Chapter 338 — PUBLIC WORKS

## Text

Within 5 working days after a subcontractor receives a written request from a subcontractor or supplier of his or her subcontractor or supplier with respect to a subcontract which has not been fully performed, he or she shall notify the subcontractor or supplier of his or her subcontractor or supplier in writing of the following:

1. The date the subcontractor made a specified progress payment or retainage payment to his or her subcontractor or supplier;

2. Whether the subcontractor has paid the entire amount of a specified progress payment or retainage payment to his or her subcontractor or supplier; and

3. The amount withheld by the subcontractor from a specified progress payment or retainage payment to his or her subcontractor or supplier, if any.