# Nev. Rev. Stat. § 408.319 — Report of projects for construction and maintenance: Preparation; contents; revision; public inspection.

- **Citation**: Nev. Rev. Stat. § 408.319
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-408.html](https://www.leg.state.nv.us/nrs/NRS-408.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-34/chapter-408/section-408-319](https://corpuslaw.us/codes/nevada/title-34/chapter-408/section-408-319)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-34/chapter-408/section-408-319](https://corpuslaw.us/codes/nevada/title-34/chapter-408/section-408-319)

## Hierarchy

Title 34 — EDUCATION > Chapter 408 — HIGHWAYS, ROADS AND
TRANSPORTATION FACILITIES

## Text

1. The Department shall prepare and make available for public inspection a report of its projects for the construction and maintenance of highways. The report must include:

(a) A description of the Departments work in progress and its proposed projects;

(b) The cost of each project, including the anticipated cost for:

(1) The acquisition of rights-of-way;

(2) Design and engineering; and

(3) Construction; and

(c) The estimated starting dates for each project and the components of each project.

2. The report must be revised every 6 months to indicate any change in the cost of a project or the component of a project, and any change in the starting or completion date of a project.

3. The Department shall make the report available for public inspection at its office during normal business hours.