# Nev. Rev. Stat. § 704.7725 — Utility required to submit request to Commission to establish time-variant rate schedule designed to expand use of energy storage systems; review and approval or denial of request by Commission.

- **Citation**: Nev. Rev. Stat. § 704.7725
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-704.html](https://www.leg.state.nv.us/nrs/NRS-704.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-7725](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-7725)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-7725](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-7725)

## Hierarchy

Title 58 — ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES > Chapter 704 — REGULATION OF PUBLIC
UTILITIES GENERALLY

## Text

1. An electric utility that primarily serves densely populated counties shall, on or before August 1, 2017, file with the Commission in a manner authorized by NRS 704.110 a request that the Commission establish an optional time-variant rate schedule for customers, including, without limitation, customer-generators who acquire an energy storage system.

2. An electric utility that primarily serves less densely populated counties shall, on or before January 16, 2018, file with the Commission in a manner authorized by NRS 704.100 a request that the Commission establish an optional time-variant rate schedule for customers, including, without limitation, customer-generators who acquire an energy storage system.

3. A request filed pursuant to subsection 1 or 2 must be designed to expand and accelerate the development and use of energy storage systems in this State.

4. The Commission:

(a) Shall review each request filed pursuant to subsection 1 or 2;

(b) May approve each request that the Commission finds to be in the public interest; and

(c) Not later than March 15, 2018, shall issue a written order approving or denying each request filed pursuant to subsection 1 or 2.

5. As used in this section:

(a) Electric utility that primarily serves densely populated counties has the meaning ascribed to it in NRS 704.110 .

(b) Electric utility that primarily serves less densely populated counties has the meaning ascribed to it in NRS 704.110 .

(c) Energy storage system means any commercially available technology that is capable of retaining energy, storing the energy for a period of time and delivering the energy after storage, including, without limitation, by chemical, thermal or mechanical means.

(d) Time-variant rate schedule means a rate schedule that incorporates different rates for different times of day during which electricity may be used by a customer or fed back to the utility by the customer.