> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Nev. Rev. Stat. § 704.79886 — Commission to require transmission providers to join regional transmission organization; waiver or delay of requirement.

- **Citation**: Nev. Rev. Stat. § 704.79886
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-704.html](https://www.leg.state.nv.us/nrs/NRS-704.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-79886](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-79886)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-79886](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-79886)

## Hierarchy

Title 58 — ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES > Chapter 704 — REGULATION OF PUBLIC
UTILITIES GENERALLY

## Text

1. Except as otherwise provided in subsection 2, the Commission shall require every transmission provider in this State to join a regional transmission organization on or before January 1, 2030.

2. Upon application by a transmission provider, the Commission may waive or delay the requirement in subsection 1 if:

(a) The transmission provider files an application with the Commission on or before January 1, 2027, requesting the waiver or delay;

(b) The transmission provider demonstrates:

(1) That the transmission provider has made all reasonable efforts to comply with the requirement but is unable to find a viable and available regional transmission organization that the transmission provider can join on or before January 1, 2030; or

(2) That it would not be in the best interests of the transmission provider and its customers to join a regional transmission organization on or before January 1, 2030; and

(c) The Commission determines that it is in the public interest to grant the requested waiver or delay.