> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# Nev. Rev. Stat. § 704.873 — Commission has exclusive jurisdiction to determine need for utility facilities of certain public utilities; other permitting entities precluded from considering need.

- **Citation**: Nev. Rev. Stat. § 704.873
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-704.html](https://www.leg.state.nv.us/nrs/NRS-704.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-873](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-873)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-873](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-873)

## Hierarchy

Title 58 — ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES > Chapter 704 — REGULATION OF PUBLIC
UTILITIES GENERALLY

## Text

If a public utility that is subject to the provisions of NRS 704.736 to 704.754, inclusive, applies to the Commission for a permit for the construction of a utility facility:

1. The Commission has exclusive jurisdiction with regard to the determination of whether a need exists for the utility facility; and

2. No other permitting entity may consider, in its review of any application for a permit, license or other approval for the construction of the utility facility, whether a need exists for the utility facility.