# Nev. Rev. Stat. § 704.891 — Reports to be filed with Commission by person holding permit who is not public utility.

- **Citation**: Nev. Rev. Stat. § 704.891
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-704.html](https://www.leg.state.nv.us/nrs/NRS-704.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-891](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-891)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-891](https://corpuslaw.us/codes/nevada/title-58/chapter-704/section-704-891)

## Hierarchy

Title 58 — ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES > Chapter 704 — REGULATION OF PUBLIC
UTILITIES GENERALLY

## Text

1. Any person other than a public utility who receives a permit issued by the Commission pursuant to NRS 704.820 to 704.900 , inclusive, shall, as provided in subsection 2, file with the Commission reports which contain:

(a) The location, nature and capacity of that facility;

(b) The anticipated date for commercial operation of that facility;

(c) Information regarding whether any public utility in this state has contracted for the purchase of the capacity or other services of that facility; and

(d) Information regarding whether any capacity or other services of that facility is available for purchase by public utilities in this state.

2. The reports required by subsection 1 must be filed:

(a) On or before the date on which construction of a utility facility is commenced; and

(b) On a date not later than:

(1) Twelve months before the scheduled date of commercial operation of that facility; or

(2) Thirty days before the actual date of commercial operation of that facility,

Ê whichever is earlier.