# Nev. Rev. Stat. § 108.22116 — Completion of the work of improvement defined.

- **Citation**: Nev. Rev. Stat. § 108.22116
- **Node Type**: section
- **Jurisdiction**: Nevada (state)
- **Code Body**: Nevada Revised Statutes (Nev. Rev. Stat.)
- **Official Source**: [https://www.leg.state.nv.us/nrs/NRS-108.html](https://www.leg.state.nv.us/nrs/NRS-108.html)
- **Canonical URL**: [https://corpuslaw.us/codes/nevada/title-9/chapter-108/section-108-22116](https://corpuslaw.us/codes/nevada/title-9/chapter-108/section-108-22116)
- **Semantic URL**: [https://corpuslaw.us/codes/nevada/title-9/chapter-108/section-108-22116](https://corpuslaw.us/codes/nevada/title-9/chapter-108/section-108-22116)

## Hierarchy

Title 9 — SECURITY INSTRUMENTS OF PUBLIC UTILITIES;
MORTGAGES; DEEDS OF TRUST; OTHER LIENS > Chapter 108 — STATUTORY LIENS

## Text

Completion of the work of improvement means:

1. The occupation or use by the owner, an agent of the owner or a representative of the owner of the work of improvement, accompanied by the cessation of all work on the work of improvement;

2. The acceptance by the owner, an agent of the owner or a representative of the owner of the work of improvement, accompanied by the cessation of all work on the work of improvement; or

3. The cessation of all work on a work of improvement for 30 consecutive days, provided a notice of completion is timely recorded and served and the work is not resumed under the same contract.