# NMSA 1978, § 13-1-105 — Competitive sealed bids; receipt and acceptance of bids

- **Citation**: NMSA 1978, § 13-1-105
- **Node Type**: section
- **Jurisdiction**: New Mexico (state)
- **Code Body**: New Mexico Statutes Annotated 1978 (through the 2026 session) (NMSA 1978)
- **Official Source**: [https://nmonesource.com/nmos/nmsa-unanno/en/item/18513/index.do#!b/13-1-105](https://nmonesource.com/nmos/nmsa-unanno/en/item/18513/index.do#!b/13-1-105)
- **Canonical URL**: [https://corpuslaw.us/codes/new-mexico/chapter-13/article-1/section-13-1-105](https://corpuslaw.us/codes/new-mexico/chapter-13/article-1/section-13-1-105)
- **Semantic URL**: [https://corpuslaw.us/codes/new-mexico/chapter-13/article-1/section-13-1-105](https://corpuslaw.us/codes/new-mexico/chapter-13/article-1/section-13-1-105)

## Hierarchy

Chapter 13 — Public Purchases and Property > Article 1 — Procurement

## Text

13-1-105. Competitive sealed bids; receipt and acceptance of bids

A. Bids shall be unconditionally accepted for consideration for award without alteration or correction, except as authorized in the Procurement Code. In addition to the requirement for the prime contractor and subcontractors to be registered as provided in Section 13-4-13.1 NMSA 1978, bids shall be evaluated based on the requirements set forth in the invitation for bids, which requirements may include criteria to determine acceptability such as inspection, testing, quality, workmanship, delivery and suitability for a particular purpose. Those criteria such as discounts, transportation costs and total or life-cycle costs that will affect the bid price shall be objectively measurable, which shall be defined by rule. The invitation for bids shall set forth the evaluation criteria to be used. No criteria may be used in bid evaluation that are not set forth in the invitation for bids. A bid submitted by a prime contractor that was not registered as required by Section 13-4-13.1 NMSA 1978 shall not be considered for award. A bid submitted by a registered prime contractor that includes any subcontractor that is not registered in accordance with that section may be considered for award following substitution of a registered subcontractor for any unregistered subcontractor in accordance with Section 13-4-36 NMSA 1978.

B. If the lowest responsible bid has otherwise qualified, and if there is no change in the original terms and conditions, the lowest bidder may negotiate with the purchaser for a lower total bid in order to avoid rejection of all bids for the reason that the lowest bid was up to ten percent higher than budgeted project funds. Such negotiation shall not be allowed if the lowest bid was more than ten percent over budgeted project funds.

Laws 1984, ch. 65, § 78; 1987, ch. 348, § 4; 2005, ch. 98, § 1.