# NMSA 1978, § 72-5-8 — Construction of works; additional time

- **Citation**: NMSA 1978, § 72-5-8
- **Node Type**: section
- **Jurisdiction**: New Mexico (state)
- **Code Body**: New Mexico Statutes Annotated 1978 (through the 2026 session) (NMSA 1978)
- **Official Source**: [https://nmonesource.com/nmos/nmsa-unanno/en/item/18575/index.do#!b/72-5-8](https://nmonesource.com/nmos/nmsa-unanno/en/item/18575/index.do#!b/72-5-8)
- **Canonical URL**: [https://corpuslaw.us/codes/new-mexico/chapter-72/article-5/section-72-5-8](https://corpuslaw.us/codes/new-mexico/chapter-72/article-5/section-72-5-8)
- **Semantic URL**: [https://corpuslaw.us/codes/new-mexico/chapter-72/article-5/section-72-5-8](https://corpuslaw.us/codes/new-mexico/chapter-72/article-5/section-72-5-8)

## Hierarchy

Chapter 72 — Water Law > Article 5 — Appropriation and Use of Surface Water

## Text

72-5-8. Construction of works; additional time

Construction of works shall be diligently prosecuted in order that the project may be completed within the time limit set by the state engineer in the permit, provided that the state engineer may upon the request of the applicant allow additional time for the completion of works equal to the time during which work was prevented by acts of God, operation of law or other causes beyond the control of the applicant.

Laws 1907, ch. 49, § 29; Code 1915, § 5687; C.S. 1929, § 151-138; Laws 1941, ch. 126, § 11; 1941 Comp., § 77-507; 1953 Comp., § 75-5-7.