> For AI agents: read the machine-readable documentation index at [https://corpuslaw.us/llms.txt](https://corpuslaw.us/llms.txt) or the single-file full reference at [https://corpuslaw.us/llms-full.txt](https://corpuslaw.us/llms-full.txt).

# 61 O.S. § 224 — Payment of subcontractor or sub-contractor or supplier - Time limit.

- **Citation**: 61 O.S. § 224
- **Node Type**: section
- **Jurisdiction**: Oklahoma (state)
- **Code Body**: Oklahoma Statutes (through the 2024 or 2025 session, by title) (O.S.)
- **Official Source**: [https://www.oklegislature.gov/OK_Statutes/CompleteTitles/os61.pdf#page=72](https://www.oklegislature.gov/OK_Statutes/CompleteTitles/os61.pdf#page=72)
- **Canonical URL**: [https://corpuslaw.us/codes/oklahoma/title-61/section-61-224](https://corpuslaw.us/codes/oklahoma/title-61/section-61-224)
- **Semantic URL**: [https://corpuslaw.us/codes/oklahoma/title-61/section-61-224](https://corpuslaw.us/codes/oklahoma/title-61/section-61-224)

## Hierarchy

Title 61 — PUBLIC BUILDINGS AND PUBLIC WORKS

## Text

61-224. Payment of subcontractor or sub-contractor or supplier - Time limit.

A. If a subcontractor or material supplier has performed in accordance with the provisions of a construction contract, the prime contractor shall make payment to the subcontractor or material supplier no later than ten (10) calendar days after the prime contractor receives its corresponding payment for the work performed.

B. If a sub-subcontractor or material supplier has performed in accordance with the provisions of a construction contract, the sub- subcontractor or material supplier shall be entitled to receive payment no later than seven (7) calendar days after subcontractor receives its corresponding payment for the work performed.

Added by Laws 2004, c. 256, § 4, eff. Nov. 1, 2004. Renumbered from Title 15, § 624 by Laws 2005, c. 92, § 6, eff. Nov. 1, 2005.
