# Or. Rev. Stat. § 758.545 — Electric utility required to make good faith effort to transmit energy; remedy

- **Citation**: Or. Rev. Stat. § 758.545
- **Node Type**: section
- **Jurisdiction**: Oregon (state)
- **Code Body**: Oregon Revised Statutes (2025 edition) (ORS)
- **Official Source**: [https://www.oregonlegislature.gov/bills_laws/ors/ors758.html#758.545](https://www.oregonlegislature.gov/bills_laws/ors/ors758.html#758.545)
- **Canonical URL**: [https://corpuslaw.us/codes/oregon/title-57/chapter-758/section-758-545](https://corpuslaw.us/codes/oregon/title-57/chapter-758/section-758-545)
- **Semantic URL**: [https://corpuslaw.us/codes/oregon/title-57/chapter-758/section-758-545](https://corpuslaw.us/codes/oregon/title-57/chapter-758/section-758-545)

## Hierarchy

Title 57 — Utility Regulation > Chapter 758 — Utility Rights of Way and Territory Allocation; Cogeneration

## Text

758.545. Electric utility required to make good faith effort to transmit energy; remedy

(1) If an electric utility fails to make a good faith effort to comply with a request from a qualifying facility to transmit energy or energy and capacity produced by the qualifying facility to another electric utility or to the Bonneville Power Administration, the electric utility shall purchase the qualifying facility’s energy or energy and capacity at a price which is the higher of:

(a) The electric utility’s avoided cost; or

(b) The index rate.

(2) As used in this section, “good faith effort” shall be demonstrated by the electric utility’s publication of a generally applicable, reasonable policy of the electric utility to allow a qualifying facility to use the electric utility’s transmission facilities on a cost-related basis.

1983 c.799 §5