# Tex. GOV'T Code § 2272.004. — OPPORTUNITY TO INSPECT AND CORRECT.

- **Citation**: Tex. GOV'T Code § 2272.004.
- **Node Type**: section
- **Jurisdiction**: Texas (state)
- **Code Body**: Texas Statutes (Tex. Code)
- **Official Source**: [https://statutes.capitol.texas.gov/](https://statutes.capitol.texas.gov/)
- **Canonical URL**: [https://corpuslaw.us/codes/texas/government-code/title-10/chapter-2272/section-2272-004](https://corpuslaw.us/codes/texas/government-code/title-10/chapter-2272/section-2272-004)
- **Semantic URL**: [https://corpuslaw.us/codes/texas/government-code/title-10/chapter-2272/section-2272-004](https://corpuslaw.us/codes/texas/government-code/title-10/chapter-2272/section-2272-004)

## Hierarchy

Title 10 — GENERAL GOVERNMENT > Chapter 2272 — CERTAIN CONSTRUCTION LIABILITY CLAIMS

## Text

(a)  Before bringing an action asserting a claim to which this chapter applies, the governmental entity must allow each party with whom the governmental entity has a contract for the design or construction of an affected structure and who is subject to the claim and any known subcontractor or supplier who is subject to the claim:

(1)  a reasonable opportunity to inspect any construction defect or related condition identified in the report for a period of 30 days after sending the report required by Section 2272.003 ; and

(2)  at least 120 days after the inspection to:

(A)  correct any construction defect or related condition identified in the report; or

(B)  enter into a separate agreement with the governmental entity to correct any construction defect or related condition identified in the report.

(b)  The governmental entity is not required to allow a party to make a correction or repair under Subsection (a) if:

(1)  the party:

(A)  is a contractor and cannot provide payment and performance bonds to cover the corrective work;

(B)  cannot provide liability insurance or workers' compensation insurance;

(C)  has been previously terminated for cause by the governmental entity; or

(D)  has been convicted of a felony; or

(2)  the governmental entity previously complied with the process required by Subsection (a) regarding a construction defect or related condition identified in the report and:

(A)  the defect or condition was not corrected as required by Subsection (a)(2)(A) or an agreement under Subsection (a)(2)(B); or

(B)  the attempt to correct the construction defect or related condition identified in the report resulted in a new construction defect or related condition.

Added by Acts 2019, 86th Leg., R.S., Ch. 1287 (H.B. 1999 ), Sec. 1, eff. June 14, 2019.