# Tex. PROP Code § 53.234. — TIME FOR NOTICE.

- **Citation**: Tex. PROP Code § 53.234.
- **Node Type**: section
- **Jurisdiction**: Texas (state)
- **Code Body**: Texas Statutes (Tex. Code)
- **Official Source**: [https://statutes.capitol.texas.gov/](https://statutes.capitol.texas.gov/)
- **Canonical URL**: [https://corpuslaw.us/codes/texas/property-code/title-5/chapter-53/section-53-234](https://corpuslaw.us/codes/texas/property-code/title-5/chapter-53/section-53-234)
- **Semantic URL**: [https://corpuslaw.us/codes/texas/property-code/title-5/chapter-53/section-53-234](https://corpuslaw.us/codes/texas/property-code/title-5/chapter-53/section-53-234)

## Hierarchy

Title 5 — EXEMPT PROPERTY AND LIENS > Chapter 53 — MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN

## Text

The lien claimant must give notice not later than the 15th day of the second month following the month in which the labor was performed or the material furnished.

Acts 2009, 81st Leg., R.S., Ch. 1304 (H.B. 2515 ), Sec. 3, eff. September 1, 2009.