Waiver of procedures and time schedules
N.D. Cent. Code § 49-22.1-05
in effect49-22.1-05. Waiver of procedures and time schedules
Any utility that proposes to construct a gas or liquid energy conversion facility or a gas or
liquid transmission facility within the state may make an application to the commission for a
waiver of any of the procedures or time schedules set forth in this chapter or in the rules
adopted pursuant to this chapter. The commission, upon a finding that the proposed facility is of
a length, design, location, or purpose that it will produce minimal adverse effects, or, upon a
finding that a demonstrable emergency exists, may issue an order waiving specified procedures
and time schedules required by this chapter or by the rules adopted pursuant to this chapter,
including applications, notices, and hearings, and may forthwith issue a certificate of site
compatibility, a certificate of corridor compatibility, or a route permit, with such conditions as the
commission may require.
Source: Open US Law by Vaquill AI (CC BY 4.0)URL: https://ndlegis.gov/cencode/t49c22-1.pdf#nameddest=49-22p1-05Fetched: 10/16/2026