What else must I report if I have a deviation from the requirement to have a qualified operator accessible?
40 C.F.R. § 60.3054
in effect(a) If all qualified operators are not accessible for 2 weeks or more, you must take the two actions in paragraphs (a)(1) and (2) of this section.
(1) Submit a notification of the deviation within 10 days that includes the three items in paragraphs (a)(1)(i) through (iii) of this section.
(i) A statement of what caused the deviation.
(ii) A description of what you are doing to ensure that a qualified operator is accessible.
(iii) The date when you anticipate that a qualified operator will be available.
(2) Submit a status report to EPA every 4 weeks that includes the three items in paragraphs (a)(2)(i) through (iii) of this section.
(i) A description of what you are doing to ensure that a qualified operator is accessible.
(ii) The date when you anticipate that a qualified operator will be accessible.
(iii) Request approval from EPA to continue operation of the OSWI unit.
(b) If your unit was shut down by EPA, under the provisions of § 60.3020(c)(2), due to a failure to provide an accessible qualified operator, you must notify EPA that you are resuming operation once a qualified operator is accessible.