REPORT ON COMPLETED HIGHWAY CONSTRUCTION PROJECTS.
Tex. TRANSP Code § 201.812.
in effect(a) The department shall semiannually publish on the department's Internet website a report on all highway construction projects, listed by department district, that have been completed.
(b) The report required by Subsection (a) must, for each project listed in the report:
(1) specify whether the project was completed:
(A) on schedule, ahead of schedule, or behind schedule; and
(B) on budget, under budget, or over budget; and
(2) include any change orders.
Added by Acts 2017, 85th Leg., R.S., Ch. 533 (S.B. 312 ), Sec. 13, eff. September 1, 2017.
SUBCHAPTER K. ROAD AND HIGHWAY USE; SIGNS