Cal. Public Contract Code - PCC § 21568.9.
in effectIf the district elects to award a project pursuant to this article, retention proceeds withheld by the district from the design-build entity or Construction Manager/General Contractor shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation of bids.