Arbitration
30 ILCS 557/15
in effect(30 ILCS 557/15) Sec. 15. Arbitration. A contractor and governmental entity may, by mutual agreement, arbitrate the contractor's entitlement to recover the actual increase in contract time or costs incurred because of a physical condition at the site. The judgment rendered may be entered in any court having jurisdiction over the matter. (Source: P.A. 91-647, eff. 11-30-99.)
Source: Open US Law by Vaquill AI (CC BY 4.0)URL: https://www.ilga.gov/legislation/ilcs/ilcs.aspFetched: 10/17/2026