Project review committee — Duties.
RCW 39.10.250
in effectThe committee shall: (1) Certify, or renew certification for, public bodies to use design-build or general contractor/construction manager contracting procedures, or both; (2) Review and approve the use of the design-build or general contractor/construction manager contracting procedures on a project by project basis for public bodies that are not certified under RCW 39.10.270 ; (3) Review and approve the use of alternative subcontractor selection under RCW 39.10.385 on a project-by-project basis for public bodies that are not certified under RCW 39.10.270 , which review and approval may be concurrent with project approval; and (4) Review and approve not more than two design-build demonstration projects that include procurement of operations and maintenance services for a period longer than three years.
The committee shall:
(1) Certify, or renew certification for, public bodies to use design-build or general contractor/construction manager contracting procedures, or both;
(2) Review and approve the use of the design-build or general contractor/construction manager contracting procedures on a project by project basis for public bodies that are not certified under RCW 39.10.270 ;
(3) Review and approve the use of alternative subcontractor selection under RCW 39.10.385 on a project-by-project basis for public bodies that are not certified under RCW 39.10.270 , which review and approval may be concurrent with project approval; and
(4) Review and approve not more than two design-build demonstration projects that include procurement of operations and maintenance services for a period longer than three years.