New statement demand by entity; effect of noncompliance; incomplete or false information in prequalification application
Ind. Code § 36-1-9.5-22
in effectSec. 22. (a) An entity may at any time during which a certificate of qualification is in effect demand a new statement. If a contractor does not provide a new statement not later than sixty (60) days after the request is made, the entity may void the contractor's certificate of qualification.
(b) If a contractor fails to provide complete and true information in an application, the application for prequalification shall be rejected.
As added by P.L.85-1991, SEC.3.
Source: Open US Law by Vaquill AI (CC BY 4.0)URL: https://iga.in.gov/laws/2026/ic/titles/36Fetched: 10/17/2026
