in effectA direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times:
(a)
Ninety days after completion of the work of improvement.
(b)
Sixty days after the owner records a notice
of completion or cessation.