Application shield.
Del. Code tit. 7, § 6098
in effectExcept for sources required to have a permit before construction or modification under the applicable requirements of this subchapter, if an applicant has submitted a timely and complete application for a permit required by this title (including renewals), but final action has not been taken on such application, the source’s failure to have a permit shall not be a violation of this subchapter, unless the delay in final action was due to the failure of the applicant to timely submit information required or requested to process the application.
Source: DE Code (Official Site)URL: https://delcode.delaware.gov/title7/c060/sc08/index.htmlFetched: 10/4/2026