Scope of subpart.
10 C.F.R. § 52.12
in effectEffective: 2024-07-01This subpart sets out the requirements and procedures applicable to Commission issuance of an early site permit for approval of a site for one or more nuclear power facilities separate from the filing of an application for a construction permit or combined license for the facility.
Source: eCFRURL: https://www.ecfr.gov/api/versioner/v1/full/2024-07-01/title-10.xmlFetched: 7/26/2026