Phased permitting.
Municipal Code of Chicago § 14A-1-105.9.9
in effect14A-1-105.9.9 Phased permitting.
On and after December 1, 2026, the building official may allow a permit application that seeks a permit for the second or subsequent phase of a project for which the first phase permit was issued under the 2022 Chicago Energy Transformation Code to be issued and built under that code. The building official may designate, by rule, criteria for application of this provision.
(Amend Coun. J. 9-21-22, p. 52080, Art. II, § 1; Amend Coun. J. 6-17-26, p. 45214, Art. IV, § 8)
Source: City of Chicago, Municipal Code of Chicago (American Legal Publishing, codelibrary.amlegal.com)URL: https://codelibrary.amlegal.com/codes/chicago/latest/chicago_il/0-0-0-2703891Fetched: 10/24/2026