Phased permitting.
Municipal Code of Chicago § 14A-1-105.2.6
in effect14A-1-105.2.6 Phased permitting.
On and after August 1, 2020, the building official may allow a permit application that seeks a permit for the second or subsequent phase of a construction project for which an issued permit for the first phase was applied for before August 1, 2020, to be issued and built in accordance with all construction requirements applicable to the previously-issued permit. The building official may designate, by rule, criteria for application of this provision.
(Amend Coun. J. 10-7-20, p. 21791, Art. I, § 2)
Source: City of Chicago, Municipal Code of Chicago (American Legal Publishing, codelibrary.amlegal.com)URL: https://codelibrary.amlegal.com/codes/chicago/latest/chicago_il/0-0-0-2660493Fetched: 10/24/2026