All fees shall be paid in accordance with the following fee schedule:
Permit or Activity Fee Other Charges Maximum Duration per Permit Maximum Distance per Permit Maximum Width per Permit
Street Opening Permits – General:
Normal street $135.00 15 days 300 linear ft. (lin. ft.) 12 feet
Protected street $135.00 $245.00 inspection fee 15 days 300 lin. ft. 12 feet
Emergency work $45.00 2 business days 300 lin. ft. 12 feet
Specific Types of Street Opening Permits:
Open sidewalk to install foundation $135.00 30 days 300 lin. ft. sidewalk (SW) width
Major installations – electric conduit $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. 12 feet
Major installations – gas pipe $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. 12 feet
Major installations – steam pipe $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. 12 feet
Major installations – telephone line $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. 12 feet
Transformer vault-in roadway $135.00, $380.00 protected street 15 days to 30 days 300 lin. ft. variable
Transformer vault-in sidewalk $135.00 15 days to 30 days 300 lin. ft. SW width
Installation and/or Removal of poles $135.00 30 days 2 sw flags SW width
Major installations – water $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. 12 feet
Major installations – cable $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. 12 feet
Major installations – sewer $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. 12 feet
Rapid transit construct/alteration $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) 300 lin. ft. Variable or SW width
Installation of public telephone stanchion $135.00 30 days Not Applicable SW width
Installation of newsstand $135.00 30 days As per approved plans As per approved plans
Repair water connections/mains $135.00, $380.00 protected street $10.00 minimum for tunneling and/or jacking. Excess over 1st 10 ft., $1.00 per ft. 15 days to 30 days 300 lin. ft. 12 feet
Repair sewer connections/main $135.00, $380.00 protected street 15 days to 30 days 300 lin. ft. 12 feet
Repair water and sewer connection/mains $135.00, $380.00 protected street 15 days to 30 days 300 lin. ft. 12 feet
Install or replace fuel oil line $135.00 15 days 300 lin. ft. SW width
Vault construction, alteration, or repair $135.00 30 days 300 lin. ft. As per approved plan
Reset, replace, install or repair curb $135.00 30 days As required, up to 300 lin. ft. Not applicable
Pave roadway $135.00 15 days 300 lin. ft. & as per approved plan As per approved plan
Tree pit $135.00 30 days 300 lin. ft. Variable based on SW width
Construct or alter utility access chamber $135.00, $380.00 protected street 15 days 300 lin. ft. 12 feet
Adjust hardware casting $135.00 15 days 300 lin. ft. 12 feet
Access to utility chamber in restricted zone during restricted hours $30.00 Uninterrupted emergency period 300 lin. ft. 12 feet
Repair gas connections/mains $135.00, $380.00 protected street 30 days 300 lin. ft. 12 feet or SW width
Repair steam connection/mains $135.00, $380.00 protected street 30 days 300 lin. ft. 12 feet or SW width
Repair electric/communication lines $135.00, $380.00 protected street 30 days 300 lin. ft. Not applicable
Test pits, cores or boring $135.00, $380.00 protected street 15 days 300 lin. ft. 12 feet
Conduit construction (cable, telecommunication) & franchise $135.00, $380.00 protected street 15 days 300 lin. ft. As per approved plans
Major installation - franchise $135.00, $380.00 protected street 30 days (90 days with OCMC approval.) As per approved plans SW width
Erect canopy $135.00 30 days Not applicable Not applicable
Install street furniture $135.00 30 days Not applicable Not applicable
Land fill $135.00 Inspection fee of $25.00 for 1st 400 cubic yards. Excess over 400 cy at $0.05 per cy. 30 days Not applicable 12 feet
Private sewer $135.00, $380.00 protected street 30 days 300 lin. ft. Not applicable
Install fence $135.00 30 days 300 lin. ft. Not applicable
Install traffic signals $135.00, $380.00 protected street 30 days 300 lin. ft. 12 feet or SW width
Install or repair petroleum pipelines/monitoring and recovery systems $135.00, $380.00 protected street 30 days 300 lin. ft. SW width
Installation of fire alarm box $135.00 30 days Not applicable
Fee for review of request to work during an embargo period $135.00 As per Division of Franchises
Installation of bus shelter $135.00 30 days As per Division of Franchises
Construction Activity Permits Types of Construction Activity Permits:
Place material on street $50.00 $300.00 per month inspection fee 3 months 300 linear ft. but not more than 80% frontage may be encumbered. 8 feet
Crossing sidewalk $50.00 3 months 2 crossings at 12 ft. wide within 300 linear ft. SW width
Place crane on street $50.00 per week or part thereof. $100.00 per inspection fee 1 week Variable Not more than one third width of roadway
Place equipment other than crane on street $50.00 3 months 300 lin. ft. 12 feet
Place shanty or trailer on street $50.00 3 months Variable 12 feet
Temporary pedestrian walk in roadway $50.00 3 months 300 lin. ft.
Install or change pavement markings, construction signs and supports $50.00 90 days
Hang temporary festoon/holiday lighting and/or other temporary lighting $50.00 90 days
Temporary closing of roadway $50.00 3 months
Temporary sidewalk closing $50.00 3 months
Placement of containers for construction waste debris $50.00 90 days 300 lin. ft. 12 feet
Sidewalk Construction Permits:
Repair/construct sidewalk $70.00 30 days 300 lin. ft. or per block and lot SW width
Licenses:
Vault License $35.00 $2.00 per sq. ft.
Canopy Permits $50.00 1 year
Canopy in connection with a sidewalk cafe license $25.00 1 year
Miscellaneous Charges and Fees:
Subpoenas $15.00
Removal of banners, canopies, signs and other encroachments and obstructions cost of labor and materials
Storage fee for removed banners, canopies, signs and other encroachments and obstructions $15.00 per day
CARs $40.00
Backcharges and JETS $134.00 per sq. yd.
Extension of Permit $40.00 14 days
Place commercial refuse container on street $30.00 5 consecutive days 9 feet
Application review fee for placement of commercial refuse container on street in restricted area as defined in 34 RCNY § 2-14(f)(4) $30.00 per application
Reissuance of permit within three business days $15.00 duration of original permit
Renew temporary security structure $50.00 Six months 300 lin. ft. Not applicable
Filing of Sidewalk, Curb and Roadway Application (SCARA) – Plan Type A No fee one year
Filing of SCARA – Plan Type B $35.00 filing fee one year
Filing of SCARA – Plan Type C $2.00 per lin. ft. one year
Filing of SCARA – Plan Type D $4.00 per lin. ft. one year
Filing of SCARA – Plan Type E $4.00 per lin. ft. one year
Filing of SCARA – Plan Type F $8.00 per lin. ft. one year
Install temporary security structure $50.00 One year 300 lin. ft. Not applicable
City adjustment of street hardware to meet pavement $125.00 Not applicable Not applicable Not applicable
Install overhead shunt $0.00 90 days Building to nearest pole or pole to nearest other pole Not applicable
Install street shunt $50.00 90 days 300 lin. ft. Not applicable
Install wrap-around shunt $0.00 90 days Per shaft Not applicable