Denial of permit.
Municipal Code of Chicago § 14A-4-405.6
in effect14A-4-405.6 Denial of permit.
On and after March 1, 2023, when a temporary structure requires both a building permit and an Outdoor Special Event Permit under Section 10-8-335 of the Municipal Code, the building official must deny the building permit if a substantially complete building permit application, including substantially complete construction documents, is not received by the building official at least 14 calendar days before the start of the event.
(Added Coun. J. 12-14-22, p. 58278, Art. II, § 8)
Source: City of Chicago, Municipal Code of Chicago (American Legal Publishing, codelibrary.amlegal.com)URL: https://codelibrary.amlegal.com/codes/chicago/latest/chicago_il/0-0-0-2699744Fetched: 10/24/2026