General.
NYC Admin. Code § 28-104.1
in effect§ 28-104.1 General.
The department shall not issue a permit pursuant to this code, or a place of assembly operation certificate pursuant to this code unless and until it approves all required construction documents for such work. The department shall not issue an electrical work permit pursuant to the New York city electrical code for fire and emergency alarm systems, solar panels and wind turbines unless and until it approves all required construction documents for such work. Such construction documents shall be prepared by or under the supervision of a registered design professional as required by this code. An application for an associated work permit shall not be submitted to the department until all required construction documents have been approved.
Source: City of New York, Charter, Administrative Code and Rules (American Legal Publishing XML export, codelibrary.amlegal.com)URL: https://codelibrary.amlegal.com/codes/newyorkcity/latest/NYCadmin/0-0-0-155911Fetched: 10/24/2026