Ventilation inspections.
Municipal Code of Chicago § 14A-5-502.8
in effect14A-5-502.8 Ventilation inspections.
The permit holder must notify the building official when mechanical ventilation work done pursuant to a permit is ready for the following types of inspections:
1. Rough inspection, after the roof, framing, fireblocking, firestopping, draftstopping, and bracing is in place and all ducting and other components to be concealed are complete, and before the installation of wall or ceiling membranes.
2. Final inspection, upon completion of the ventilation system.
(Amend Coun. J. 2-19-20, p. 14473, Art. I, § 17)