Collection and remittance of linkage fees; reporting.
Denver Revised Municipal Code § 27-156
in effectSec. 27-156. - Collection and remittance of linkage fees; reporting.
(a) The responsibility for the calculation and collection of linkage fees shall reside with personnel in the department of community planning and development, and the fees required by this division shall be collected in conjunction with the administration of the city's system for issuing building permits. Any and all linkage fees applicable to a construction project shall be paid in full prior to the issuance of any building permit, excluding the shoring or excavation permit, for that project. For projects such as townhomes where units receive separate building permits, fees shall be assessed on a permit-by-permit basis. All fees collected by the department shall be remitted to the affordable housing linkage fee revenue fund as provided in section 27-150 and used exclusively for the purposes set forth therein.
(b) If, after the issuance of a building permit and collection of the applicable linkage fee but before the issuance of a certificate of occupancy, the amount of gross floor area of the construction project increases or a decision is made by the applicant to change the use of the structure to a use category for which a higher linkage fee would be imposed under section 27-153, then the applicant shall be required to pay additional linkage fees in compliance with this division.
(c) Any dispute over the applicability or calculation of the linkage fees may be appealed by the applicant for a building permit to the executive director (manager) of the department of community planning and development, who shall determine such appeals in consultation with the executive director of the department of housing stability.
(d) Linkage fees previously paid by an applicant at building permit issuance may be refunded from the affordable housing linkage fee revenue fund if it is later determined on appeal or otherwise by the executive director (manager) of community planning and development that the fees were not due and owning under this division, if a decision is made by the applicant after a building permit has been issued to reduce the gross floor area of the construction project or to change the use of the structure to a use category for which a lower linkage fee would be imposed under section 27-153, or if the building permits for the project lapse or are relinquished by the applicant without the project building built. The executive director (manager) of community planning and development shall not be obligated to make any refund under this subsection (d) unless the applicant files a written request for a refund with the executive director within sixty (60) days from the day any grounds for a refund arise.
(e) After a building permit has been issued and the applicable linkage fees have been paid, no additional fees shall be required under either of the following circumstances:
(1) If the original building permit is cancelled in order to issue a replacement building permit to change the general contractor; or
(2) If modified drawings for the construction project are submitted and logged in for review, so long as the modified drawings do not increase the overall gross floor area of the project.
(f) The departments of community planning and development and housing stability shall provide a publicly available online resources to report on linkage fee funds collected, how linkage fee funds were spent, and approved reductions and waivers as enabled in section 27-157.
(Ord. No. 625-16, § 1, 9-19-16; Ord. No. 47-20, § 39, 3-16-20; Ord. No. 426-22, § 1, 6-6-22)
Source: City and County of Denver, Revised Municipal Code and Charter (Municode Library, library.municode.com)URL: https://library.municode.com/co/denver/codes/code_of_ordinances?nodeId=TITIIREMUCO_CH27HO_ARTVDEFUAFHO_DIV2LIFE_S27-156CORELIFEREFetched: 10/27/2026