Purpose and Intent
San Diego Municipal Code § 22.3801
in effect§22.3801 Purpose and Intent
The purpose of Division 38 is to provide definitions and guidelines for the award, use, and evaluation of construction manager at risk contracts for public works projects. Under a construction manager at risk contract, the goal is to engage the construction manager at risk entity early in the design phase to provide input on costs, schedule, and constructability. The construction manager at risk entity then commits to completing the construction services portion of the project within a guaranteed maximum price and ensures the project stays within budget while managing risks.
(Added 3-15-2010 by O-19934 N.S.; effective 4-14-2010.)
(Amended 10-13-2025 by O-22005 N.S.; effective 11-12-2025.)
Source: City of San Diego Office of the City Clerk, San Diego Municipal Code and City Charter (docs.sandiego.gov PDFs)URL: https://docs.sandiego.gov/municode/MuniCodeChapter02/Ch02Art02Division38.pdf#page=1Fetched: 10/28/2026