Failure to Request Inspection.
Milwaukee Code of Ordinances § 200-30.3
in effect200-30.3. Failure to Request Inspection.
When a contractor fails to request a required inspection for a permit open for more than 6 months beyond the date of issuance, the commissioner shall send written notice to schedule the required inspection. The contractor shall be charged the fee specified in s. 200-33 for failure to schedule the inspection within 15 days of written notice from the commissioner. Failure to pay the additional fee after one notice may result in withholding future permits.
Source: City of Milwaukee Legislative Reference Bureau, Milwaukee City Charter and Code of Ordinances (city.milwaukee.gov master PDFs)URL: https://city.milwaukee.gov/ImageLibrary/Groups/ccClerk/Ordinances/Volume-2/CH200-sub4.pdf#page=7Fetched: 10/26/2026