Installation and inspection.
San Antonio City Code § 34-1232
in effectSec. 34-1232. - Installation and inspection.
(a) Construction requests. All privately-constructed mains shall be installed in strict compliance with the construction requirements of the SAWS recycled water specifications set forth in the SAWS recycled water specifications.
(b) Inspection. After installation, but prior to covering, all privately-constructed mains shall be inspected by SAWS to ensure that all construction is in accordance with SAWS recycled water specifications. It is the duty of the customer to provide reasonable notice to SAWS when a main is or will be ready for inspection.
(c) Reinspection. If the SAWS inspector finds that the main is not in accordance with SAWS recycled water specifications, then the customer shall make the necessary corrections and the work shall be submitted for reinspection. The work shall be available for reinspection within ten (10) days of the date the customer or its representative is notified of the revisions required. For each reinspection the applicant shall pay a reinspection fee as specified in SAWS recycled water specifications.
(d) Certification. Upon satisfactory completion and inspection of a main, SAWS shall issue a certificate of construction conformity. The issuance of such certificate shall evidence SAWS' acceptance of the distribution main and appurtenant improvements on SAWS' side of the recycled water meter as the property of SAWS. Such certificate is solely for the benefit of the customer and SAWS and shall not be relied upon by any third party.
(Ord. No. 87597, § 1, 3-26-98)