Permit fee.
Omaha Municipal Code § 43-154
in effectSec. 43-154. - Permit fee.
Before any permit required by this article is issued, the applicant shall pay a fee as follows:
(a) There is a $30.00 fee for all permits for dumpsters and storage units. The initial term of the permit is for 15 days. An additional fee of $30.00 is due for each additional 15-day period thereafter.
(b) For all other permits, the fee shall be as follows:
(i) On areas designated as an arterial street or higher volume, the permit holder will be responsible to pay a fee per travel or parking lane as follows:
• 300 linear feet or less shall be $15.00 per calendar day for the duration of the permit.
• 301 to 600 linear feet shall be $24.00 per calendar day for the duration of the permit.
• 601 to 900 linear feet shall be $33.00 per calendar day for the duration of the permit.
• Over 900 linear feet shall be $40.00 per calendar day for the duration of the permit.
(ii) On areas designated as a collector street or above, the permit holder will be responsible to pay a fee per travel or parking lane as follows:
• 300 linear feet or less shall be $9.00 per calendar day for the duration of the permit.
• 301 to 600 linear feet shall be $12.00 per calendar day for the duration of the permit.
• 601 to 900 linear feet shall be $15.00 per calendar day for the duration of the permit.
• Over 900 linear feet shall be $18.00 per calendar day for the duration of the permit.
(iii) For local streets, sidewalks, alleys and other right-of-way areas, the permit holder will be responsible to pay a fee per travel lane, parking lane, or walkway as follows:
• 300 linear feet shall be $6.00 per calendar day for the duration of the permit.
• 301 to 600 linear feet shall be $8.00 per calendar day for the duration of the permit.
• 601 to 900 linear feet shall be $10.00 per calendar day for the duration of the permit.
• Over 900 linear feet shall be $12.00 per calendar day for the duration of the permit.
(c) The fee shall be waived for that part of an area to be obstructed or occupied where payment in lieu of parking meter revenue is directed by the public works director.
(d) Whenever a public street, alley or sidewalk is obstructed or occupied without first obtaining a permit, the fee shall be quadruple that required for the first 15-day period.
Payment is required at time of issuance of permit. If the time period from the original permit is extended, payment is required prior to the expiration of the original permit. Refunds will be made for days paid in advance if requested usage is completed ahead of schedule.
(Ord. No. 33582, § 1(43-154), 6-27-95; Ord. No. 43054, § 4, 9-13-22)
Source: City of Omaha, Municipal Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/ne/omaha/codes/code_of_ordinances?nodeId=OMMUCOCHGEORVOII_CH43BU_ARTIVUSPUWABUOP_S43-154PEFEFetched: 10/28/2026