Assembly permit.
Denver Revised Municipal Code § 39-78
in effectSec. 39-78. - Assembly permit.
(a) Processing: Applications for assembly permits shall be processed in accordance with the provisions of this division and as provided for in rules and regulations. Historic usage scheduled events and assemblies, where the same applicant has been granted use of a particular park at a particular date, time and place for more than two (2) consecutive years, shall have priority for that park for that date, time and place.
(b) Assembly determination: Upon receipt of any application for an assembly the manager shall, within three (3) working days of receipt of a permit application requesting an assembly permit, or such shorter time as may be necessary to allow the proposed assembly to proceed, review the application and determine, in writing, whether the proposed event is an assembly as defined in section 39-76 of this article.
(c) Standards for issuance: Upon determination that the event is an assembly and complies with applicable ordinances and rules and regulations, the manager shall grant an assembly permit if the department finds that:
(1) The application for permit (including any required attachments and submissions) is fully completed, executed and contains no material falsehood or misrepresentation;
(2) The park location requested has not been reserved for any other use at the day and hour requested in the application, including without limitation previously planned or contracted for programs organized and conducted by the department, the city, the state or any other governmental agency;
(3) The scheduled event will not substantially interfere with: any other scheduled event, any other event for which a permit under this chapter has already been granted, or the providing of city services.
(d) Approval or denial. Not more than seven (7) working days after receipt of a fully completed application for a permit for an assembly, the manager shall either issue or deny the permit, and shall notify, in writing, the applicant of such issuance or denial. If, within that time period, the manager fails to notify the applicant of the denial of the permit, the permit shall be deemed to have been issued.
(Ord. No. 55-08, § 2, 2-4-08)